Del Mar College located in Corpus Christi, TX recently opened a new campus to support the growing student population. The campus has three academic buildings and a central plant building totaling 249,300 square feet of floor area. with chillers and boilers to provide district cooling and heating. The buildings are served by 16 AHUs and 200+ terminal units. The entire HVAC system and associated BAS was commissioned to ensure correct operating conditions before the campus was opened to the student population. A standard commissioning scope for this facility type typically utilizes a sampling strategy for zone equipment resulting in verification of 20% of terminal units. Claraxio was implemented to support the commissioning scope by completing automated functional performance testing (AFPT) on 100% of terminal units and monitoring-based commissioning (MBCx) on the AHUs. Claraxio utilized fault detection algorithms to document test results and develop data-backed issues for contractor resolution. The client opted to keep Claraxio installed and online to monitor system performance and periodically re-commission zone equipment using AFPT.

IMPACT

Blue line design element that zig zags facing left
  • After consulting the facility IT team, multiple Claraxio devices were installed on local BAS networks to overcome area network limitations and meet cybersecurity requirements.
  • Tests were sequenced and scheduled to automatically run without interrupting ongoing operation and occupant comfort.
  • Assisted 100% equipment test and verification for commissioning.
  • Provided comprehensive data-backed automated functional performance test reports.
  • Integrated results with existing cloud-based commissioning process management tool.

METRICS

Blue line design element that zig zags facing left
  • 205 terminal units were functionally tested within six hours.
  • Five tests were conducted on each terminal unit to identify functional issues.
  • Reduced onsite testing duration by roughly 80%.

additional images

Blue line design element that zig zags facing left
Claraxio with the BAS controller to poll sensor data
Sample terminal box commissioning test output
Summary of metrics for Greenhill Towers